OverviewMetricsImpact & ChallengesAwardsGallery

Guiding One of India’s Largest Metro Expansions Through Integrated Programme Management

Chennai
Railway
Share

Aarvee Engineering Consultants Ltd. is providing General Consultancy Services as part of the NKAB Consortium (with Nippon Koei India Ltd., Japan, and Balaji Railroad Systems Pvt. Ltd.) for the JICA-funded portion of Chennai Metro Phase II, covering Corridor 3 and Corridor 5.



The assignment supports the delivery of a 51.5 km mass rapid transit network, combining elevated and underground sections, aimed at transforming mobility across Chennai through a fast, reliable, and integrated urban transit system.

Metrics

15.8 km
+

Total corridor length studied

18
+

Corridors covered

40
+

Entry Exit Structure

4
+

Axle load

2
+

Junction & Crossing stations

2019
+

Project commencement year

Ongoing
+

Project status

Impact Highlights

  • Enables a city-wide shift to high-capacity public transport,

Key Challenges

  • Managing complex interface conditions with multiple contractors executing tunnelling and station works simultaneously
  • Coordinating operations involving 15 trench cutters and 17 tunnel boring machines (TBMs) across dense urban corridors
  • Executing 3- and 4-level underground stations in Class I hard rock strata
  • Delivering double-decker elevated sections and stations (5 locations)
  • Navigating extensive underground utility networks, including sewer, water, and stormwater systems

Awards

  • Best Project Award – Construction Health, Safety & Environment
15th CIDC Vishwakarma Awards, 2024
  • CIDC Vishwakarma Awards 2025 – Initiatives in skilling, emerging technologies, best practices, and vibrant work environment (NKAB Consortium)